FAT and SAT — Factory and Site Acceptance Tests Every BMS Project Needs
Copied to clipboard ✓
An Erode Panel Factory, a Shipment to Pune, a Day-3 Surprise
Ranjini is a QA engineer at a panel-build factory in Erode. The factory ships a 28-controller BMS panel to a pharma plant in Pune. The shipment arrives Tuesday. Commissioning begins Wednesday. By Friday, three controllers will not talk to the front-end. The panel team blames the network. The customer blames the panel. Each side investigates independently. ``` Time on site to find each fault: Controller 7 BACnet device-instance conflict 2 hours Controller 14 Wrong baud configured at factory 1 hour Controller 22 DIP switch position wrong 30 minutes ``` Ranjini reviews the factory test logs. None of the three issues had been tested. The factory test had verified power-on, basic comms, and IO continuity — but had not run the controllers as a network with their actual configuration. ``` Cost on site: 3 fault diagnoses × 1 senior engineer day each = 3 senior-engineer days Customer's project schedule slip: 2 days Customer's frustration: substantial Cost if caught at factory: Same 3 faults, fixed at the test bench in 2 hours No site visit required Schedule slip: zero ``` Catching faults early is one of the highest-leverage things a BMS project can do. The earlier the catch, the cheaper the fix. Every single one of these problems has one solution — disciplined Factory Acceptance Tests (FAT) followed by disciplined Site Acceptance Tests (SAT).FAT — Factory Acceptance Test
Where: At the panel manufacturer's factory, before shipment. When: After panel build is complete and before crating. Who: Vendor's test engineer + customer's witness representative. Output: Signed FAT report, photographs, configuration backups. ``` FAT scope (typical for a BMS panel):- Visual inspection
- Power-on test
- Controller boot
- IO point-to-point continuity
- Network communication
- Sequence sample
- Configuration backup
- Signed report
SAT — Site Acceptance Test
Where: At the customer's site, after panel installation and cable termination. When: After all field wiring is complete and before handover. Who: Vendor + integrator + customer + (for regulated sites) consultant. Output: Signed SAT report, photographs, as-built drawings. ``` SAT scope (typical):- Site visual inspection
- Field-end IO verification
- Sequence verification
- Network verification
- Failover and edge cases
- Operator training session
- Documentation handover
- Signed report
What Pharma 21 CFR Demands From Both
For pharma sites, FAT and SAT take on additional regulatory weight: ``` Each test must: - Be witnessed by a qualified person (customer + vendor + QA) - Produce a signed, time-stamped record - Reference the URS (User Requirements Specification) - Be retrievable for FDA inspection up to 7 years - Have any deviations documented and resolved with formal deviation reports - Be tied to the validation lifecycle (URS, FDS, IQ, OQ, PQ) Pharma FAT usually adds: - Validation protocol verification - 21 CFR Part 11 audit trail testing - Electronic signature workflow testing - Data integrity testing (read consistency, no tamper) - Backup and recovery testing ``` The discipline of pharma FAT/SAT raises the quality of the whole industry — the rigour developed for pharma sites makes its way into commercial best practice.How Ranjini's Factory Becomes a Better Factory
After the Pune incident, Ranjini reworks the factory FAT process: ``` Pre-FAT improvements: - Add a 3-day "system test" to the FAT scope - Test all 28 controllers as a network, with the actual BACnet device instances and Modbus addresses - Run sample sequences from the supervisor controller - Take configuration backups before shipment Process improvements: - Customer witness invited to every FAT - FAT report template extended to cover network and sequence tests - FAT signoff required before crating - JSON configuration backup attached to FAT report Six months later: - Site commissioning faults dropped from average 5 per project to 1 per project - Average commissioning duration shrank by 40 percent - Customer NPS for the factory rose noticeably ``` The factory's reputation became the reputation for clean, predictable, on-time delivery — because what shipped from the factory was actually tested, not just built.The Core Discipline
``` FAT catches: SAT catches:- Wiring errors at the panel - Wiring errors at the field
- Configuration mismatches - Sensor calibration drift
- Firmware boot issues - Site-specific protocol issues
- IO continuity failures - Network-routing errors
- Network-discovery errors - Sequence integration failures
- Sequence logic bugs - Operator training gaps
Related Topics
- What is BMS integration? — how a BMS connects with VFDs, energy meters, BACnet/Modbus devices and other building systems
- How to design a BMS system step by step — the complete BMS design methodology covering site survey, IO list, controller selection, sequence of operations
- What is a Building Management System (BMS)? — fundamentals of BMS controls and architecture for HVAC, lighting, energy and access
- What is BMS commissioning? — the disciplined commissioning process that turns a BMS install into a working building brain
- Browse all Commissioning & Integration topics — more from this section of the EnSmart BMS Library
Related Topics
- What is BMS integration? — how a BMS connects with VFDs, energy meters, BACnet/Modbus devices and other building systems
- How to design a BMS system step by step — the complete BMS design methodology covering site survey, IO list, controller selection, sequence of operations
- What is a Building Management System (BMS)? — fundamentals of BMS controls and architecture for HVAC, lighting, energy and access
- What is BMS commissioning? — the disciplined commissioning process that turns a BMS install into a working building brain
- Browse all Commissioning & Integration topics — more from this section of the EnSmart BMS Library
Related Topics
- What is BMS integration? — how a BMS connects with VFDs, energy meters, BACnet/Modbus devices and other building systems
- How to design a BMS system step by step — the complete BMS design methodology covering site survey, IO list, controller selection, sequence of operations
- What is a Building Management System (BMS)? — fundamentals of BMS controls and architecture for HVAC, lighting, energy and access
- What is BMS commissioning? — the disciplined commissioning process that turns a BMS install into a working building brain
- Browse all Commissioning & Integration topics — more from this section of the EnSmart BMS Library
Related Topics
- What is BMS integration? — how a BMS connects with VFDs, energy meters, BACnet/Modbus devices and other building systems
- How to design a BMS system step by step — the complete BMS design methodology covering site survey, IO list, controller selection, sequence of operations
- What is a Building Management System (BMS)? — fundamentals of BMS controls and architecture for HVAC, lighting, energy and access
- What is BMS commissioning? — the disciplined commissioning process that turns a BMS install into a working building brain
- Browse all Commissioning & Integration topics — more from this section of the EnSmart BMS Library
Was this answer helpful?
✓ Thanks — your feedback was recorded.